Thamesford corridor improvements
Update: September 18, 2026
First posted: July 10, 2025
Construction starting on Oxford Road 2 (Dundas Street) transportation improvements in Thamesford
Oxford County is making transportation improvements along Oxford Road 2 / Dundas Street between 15th Line and Oxford Road 119 in Thamesford. These improvements are designed to accommodate increasing traffic volumes, support continued growth in Thamesford, and improve safety for all road users.
Construction is tentatively scheduled to begin the week of September 28, and is expected to continue through November 2026. Please note that construction schedules are weather dependent and subject to change based on site conditions, contractor availability and other operational demands.
During construction, Oxford Road 2 (Dundas Street) is expected to remain open to traffic throughout construction, with two-way traffic maintained whenever possible. Temporary lane reductions, lane shifts, or short-term alternating traffic controlled by traffic-control personnel may be required to complete certain portions of the work.
To see past updates and materials for this project, please check "Documents" at right.
Pre-construction meeting
A pre-construction meeting will be held to allow the public to view drawings; learn the construction timeline, plans for managing traffic and property access in the construction area; and speak with the project team.
Thursday, September 24, 2026 | Drop in: 5:00 – 7:00 p.m.
Beaty Room (beside Oxford County Library), 165 Dundas Street, Thamesford
About this project
During construction, Oxford Road 2 is expected to remain open to traffic throughout construction, with two-way traffic maintained whenever possible. Temporary lane reductions, lane shifts, or short-term alternating traffic controlled by traffic-control personnel may be required to complete certain portions of the work.
Access to residences and businesses will be maintained as much as possible, with advance notice provided for any planned temporary access disruptions.
Work includes the following:
- new traffic signals installed at George Street;
- speed feedback signs installed near the east and west limits of Thamesford;
- existing pedestrian crossover relocated from George Street to Stanley Street;
- two-way left-turn lane installed between Stanley Street and Allen Street;
- on-street parking removed along the project corridor;
- upgrades to the existing traffic signals at Allen Street / St. Patrick Street;
- localized curb, sidewalk, boulevard, pavement-marking, and signage improvements;
Residents, businesses and road users should expect the following:
- temporary lane reductions, lane shifts and flagging operations, particularly near Stanley Street, George Street and Allen Street / St. Patrick Street;
- short-term driveway or property access interruptions. Access will be maintained as much as possible, and advance notice will be provided for planned disruptions;
- removal of on-street parking along Dundas Street within the project limits;
- increased noise, dust and construction traffic;
- short-term detours or pedestrian routing where required to complete work safely.
Please help keep our community and workers safe: respect work zones, obey traffic signs, and maintain a safe distance from equipment and vehicles entering and leaving the site.
Public information
Oxford County shared information and sought public feedback on this project in a number of ways.
- Public Information Centres were held on July 23, 2025, and June 8, 2026. A pre-construction information meeting is scheduled for September 24, 206.
- An online form accepted comments and questions after each public meeting and were addressed through Question and Answers documents.
- Questions and comments can be submitted through email at any time to the project contact, listed at right.