Update: October 2026
February 5, 2026

Update: Oxford Road 2 and 12 intersection reopened


Reconstruction work at the intersection of Oxford Road 2 (Dundas Street) and Oxford Road 12 (Mill Street) is now complete and the intersection has reopened.

Phase 1 of Oxford Road 2 reconstruction was completed in summer 2026. Work on Phase 2 is continuing.




February 5, 2026

Reconstruction of Oxford Road 2 (Dundas Street) in Woodstock

March - November 2026


Oxford County is undertaking road reconstruction work on Oxford Road 2 (Dundas Street) between Oxford Road 30 (11th Line) and Oxford Road 12 (Mill Street) in the City of Woodstock.

Construction work is tentatively scheduled to begin in March 2026 and is expected to be completed by November 2026. Work includes:

  • full road reconstruction;
  • full watermain replacement and size upgrade and select storm and sanitary replacement and size upgrade;
  • replacement of concrete curb, gutter and sidewalks;
  • improved northbound right turn lane at Oxford Road 9 and Oxford Road 2;
  • intersection improvements at Oxford Road 9 (Ingersoll Road);
  • additional traffic calming measures; and,
  • a new pedestrian crossover near the Millennium Trail System - Youth Start Trail.

Construction will take place in three (3) phases:

  • Phase 1: Oxford Road 2 (Dundas Street) from Oxford Road 30 (11th Line) and Oxford Road 9 (Ingersoll Road). Phase 1 is expected to be completed in summer 2026.
  • Phase 2A: Oxford Road 2 from Oxford Road 9 to west of Oxford Road 12.
  • Phase 2B: Intersection of Oxford Road 2 and Oxford Road 12. The intersection will be subject to a temporary four (4) week closure. Both Phase 2A and 2B are expected to be complete by November 2026.

Please note that construction schedules are weather dependent and subject to change based on site conditions, contractor availability and other operational demands.


Have your say

You can learn more about this project or submit feedback in the following ways.

Attend the Public Information Centre (PCC). A PIC took place on February 26, 2026, to allow the public to view plans and discuss the project with Public Works Engineering staff:

Comment form. Provide your comments or questions through the online comment form below.

Email your comments or questions directly to the project contact: Noah Brister, P.Eng., Project Engineer, Oxford County, nbrister@oxfordcounty.ca | 519-539-9800, ext. 3107

Online. Follow Oxford County on social media for construction updates or visit www.oxfordcounty.ca/construction

Update: October 2026
February 5, 2026

Update: Oxford Road 2 and 12 intersection reopened


Reconstruction work at the intersection of Oxford Road 2 (Dundas Street) and Oxford Road 12 (Mill Street) is now complete and the intersection has reopened.

Phase 1 of Oxford Road 2 reconstruction was completed in summer 2026. Work on Phase 2 is continuing.




February 5, 2026

Reconstruction of Oxford Road 2 (Dundas Street) in Woodstock

March - November 2026


Oxford County is undertaking road reconstruction work on Oxford Road 2 (Dundas Street) between Oxford Road 30 (11th Line) and Oxford Road 12 (Mill Street) in the City of Woodstock.

Construction work is tentatively scheduled to begin in March 2026 and is expected to be completed by November 2026. Work includes:

  • full road reconstruction;
  • full watermain replacement and size upgrade and select storm and sanitary replacement and size upgrade;
  • replacement of concrete curb, gutter and sidewalks;
  • improved northbound right turn lane at Oxford Road 9 and Oxford Road 2;
  • intersection improvements at Oxford Road 9 (Ingersoll Road);
  • additional traffic calming measures; and,
  • a new pedestrian crossover near the Millennium Trail System - Youth Start Trail.

Construction will take place in three (3) phases:

  • Phase 1: Oxford Road 2 (Dundas Street) from Oxford Road 30 (11th Line) and Oxford Road 9 (Ingersoll Road). Phase 1 is expected to be completed in summer 2026.
  • Phase 2A: Oxford Road 2 from Oxford Road 9 to west of Oxford Road 12.
  • Phase 2B: Intersection of Oxford Road 2 and Oxford Road 12. The intersection will be subject to a temporary four (4) week closure. Both Phase 2A and 2B are expected to be complete by November 2026.

Please note that construction schedules are weather dependent and subject to change based on site conditions, contractor availability and other operational demands.


Have your say

You can learn more about this project or submit feedback in the following ways.

Attend the Public Information Centre (PCC). A PIC took place on February 26, 2026, to allow the public to view plans and discuss the project with Public Works Engineering staff:

Comment form. Provide your comments or questions through the online comment form below.

Email your comments or questions directly to the project contact: Noah Brister, P.Eng., Project Engineer, Oxford County, nbrister@oxfordcounty.ca | 519-539-9800, ext. 3107

Online. Follow Oxford County on social media for construction updates or visit www.oxfordcounty.ca/construction

  • Update: Winniett Street access

    Share Update: Winniett Street access on Facebook Share Update: Winniett Street access on X (formerly Twitter) Share Update: Winniett Street access on Linkedin Email Update: Winniett Street access link

    August 24, 2026

    Beginning the week of August 24, Winniett Street between Hunter Street and Dundas Street will begin temporarily operating as a two-way street between Hunter Street and Dundas Street.

    Winniett Street north of Hunter Street remains one-way northbound. When construction on Oxford Road 2 (Dundas Street) has finished, Winniett Street will return to one-way northbound traffic only.

    August 24, 2026

    Beginning the week of August 24, Winniett Street between Hunter Street and Dundas Street will begin temporarily operating as a two-way street between Hunter Street and Dundas Street.

    Winniett Street north of Hunter Street remains one-way northbound. When construction on Oxford Road 2 (Dundas Street) has finished, Winniett Street will return to one-way northbound traffic only.

  • OR 2 (Dundas St) and OR 12 (Mill St ) intersection

    Share OR 2 (Dundas St) and OR 12 (Mill St ) intersection on Facebook Share OR 2 (Dundas St) and OR 12 (Mill St ) intersection on X (formerly Twitter) Share OR 2 (Dundas St) and OR 12 (Mill St ) intersection on Linkedin Email OR 2 (Dundas St) and OR 12 (Mill St ) intersection link

    July 21, 2026


    Phase 1 of Oxford Road 2 (Dundas Street) reconstruction in Woodstock is complete. Phase 2A began the week of July 27, with the road closure moving to the section of road between Oxford Road 9 (Ingersoll Road) and Oxford Road 12 (Mill Street).

    The main detour route will still be in place using Oxford Road 30, Oxford Road 17 and Oxford Road 59 (Vansittart Avenue). A second detour will be in place using Oxford Road 9, Main Street and Oxford Road 12 (2A detour).

    During Phase 2A, there will be no access to Oxford Road 2 from

    July 21, 2026


    Phase 1 of Oxford Road 2 (Dundas Street) reconstruction in Woodstock is complete. Phase 2A began the week of July 27, with the road closure moving to the section of road between Oxford Road 9 (Ingersoll Road) and Oxford Road 12 (Mill Street).

    The main detour route will still be in place using Oxford Road 30, Oxford Road 17 and Oxford Road 59 (Vansittart Avenue). A second detour will be in place using Oxford Road 9, Main Street and Oxford Road 12 (2A detour).

    During Phase 2A, there will be no access to Oxford Road 2 from Oxford Road 12. Local traffic will need to enter from the west using the Phase 2A detour or nearby side streets.

    We have noted questions about the pedestrian refuge island now installed just east of the overhead rail bridge. This type of feature is for pedestrian safety while crossing high traffic, multi-lane roads, and has been installed here as part of a new crosswalk to connect the City of Woodstock trail system. Please note the crosswalk will not be operational until the fall. Temporary signage will be added next week showing this section is closed to pedestrian traffic until that time.

    More information on Phase 2B will be provided closer to the start of this phase of construction.

  • Public meeting for reconstruction of OR 2 (Dundas St) in Woodstock

    Share Public meeting for reconstruction of OR 2 (Dundas St) in Woodstock on Facebook Share Public meeting for reconstruction of OR 2 (Dundas St) in Woodstock on X (formerly Twitter) Share Public meeting for reconstruction of OR 2 (Dundas St) in Woodstock on Linkedin Email Public meeting for reconstruction of OR 2 (Dundas St) in Woodstock link

    February 5, 2026

    Oxford County is undertaking road reconstruction work on Oxford Road 2 (Dundas Street) between Oxford Road 30 (11th Line) and Oxford Road 12 (Mill Street) in the City of Woodstock.

    A Public Information Centre has been scheduled to allow the public to view plans and discuss the project with Public Works Engineering staff.

    Thursday, February 26, 2026
    Drop in: 5:00 – 7:00 p.m.
    Oxford County Administration Building
    Main Lobby 21 Reeve Street, Woodstock


    Construction

    Construction work is tentatively scheduled to begin in March 2026 and is expected to be completed by November 2026. Work includes:

    February 5, 2026

    Oxford County is undertaking road reconstruction work on Oxford Road 2 (Dundas Street) between Oxford Road 30 (11th Line) and Oxford Road 12 (Mill Street) in the City of Woodstock.

    A Public Information Centre has been scheduled to allow the public to view plans and discuss the project with Public Works Engineering staff.

    Thursday, February 26, 2026
    Drop in: 5:00 – 7:00 p.m.
    Oxford County Administration Building
    Main Lobby 21 Reeve Street, Woodstock


    Construction

    Construction work is tentatively scheduled to begin in March 2026 and is expected to be completed by November 2026. Work includes:

    • full road reconstruction;
    • full watermain replacement and size upgrade and select storm and sanitary replacement and size upgrade;
    • replacement of concrete curb, gutter and sidewalks;
    • improved northbound right turn lane at Oxford Road 9 and Oxford Road 2;
    • intersection improvements at Oxford Road 9 (Ingersoll Road);
    • additional traffic calming measures; and,
    • a new pedestrian crossover near the Millennium Trail System - Youth Start Trail.


    Construction will take place in three (3) phases:

    • Phase 1: Oxford Road 2 (Dundas Street) from Oxford Road 30 (11th Line) and Oxford Road 9 (Ingersoll Road). Phase 1 is expected to be completed in summer 2026.
    • Phase 2A: Oxford Road 2 from Oxford Road 9 to west of Oxford Road 12.
    • Phase 2B: Intersection of Oxford Road 2 and Oxford Road 12. The intersection will be subject to a temporary four (4) week closure. Both Phase 2A and 2B are expected to be complete by November 2026.

    Please note that construction schedules are weather dependent and subject to change based on site conditions, contractor availability and other operational demands.


    Have your say

    You can learn more about this project or submit feedback in the following ways.

    Attend the Public Information Centre (PCC). A PIC has been scheduled to allow the public to view plans and discuss the project with Public Works Engineering staff:
    Thursday, February 26, 2026 | Drop in: 5:00 – 7:00 p.m.
    Oxford County Administration Building, Main Lobby 21 Reeve Street, Woodstock

    Comment form. Provide your comments or questions through the online comment form below.

    Email your comments or questions directly to the project contact: Noah Brister, P.Eng., Project Engineer, Oxford County, nbrister@oxfordcounty.ca | 519-539-9800, ext. 3107

    Online. Follow Oxford County on social media for construction updates or visit www.oxfordcounty.ca/construction

Page last updated: 23 Oct 2026, 08:36 AM