OR 35 (Devonshire Ave) in Woodstock

Share OR 35 (Devonshire Ave) in Woodstock on Facebook Share OR 35 (Devonshire Ave) in Woodstock on Twitter Share OR 35 (Devonshire Ave) in Woodstock on Linkedin Email OR 35 (Devonshire Ave) in Woodstock link

March 10, 2026


Oxford Road 35 (Devonshire Ave) reconstruction in Woodstock

Spring - November 2026


Oxford County is continuing a multi-year reconstruction project to improve Oxford Road 35 (Devonshire Avenue) in Woodstock.

Phase 2 of this project, beginning in spring 2026, includes construction located just east of Wellington Street to just east of Knightsbridge Road. Work includes:

  • sanitary sewer, storm sewer and watermain replacement and repairs;
  • road replacement with a three-lane cross section;
  • bike lanes and sidewalks; and,
  • traffic signal installation for a pedestrian crossing at Victoria Street.

Planned future phases include different sections of Devonshire Avenue in subsequent years, extending east to Oxford Road 4 except for the area between Lansdowne Avenue and Woodall Way.

Please note that construction schedules are weather dependent and subject to change based on site conditions, contractor availability and other operational demands.


Detour routes


Learn more

Public Information Centre (PCC). A public information meeting was held on February 24, 2026, to allow the public to view plans and discuss the project with Public Works Engineering staff.

Comment form. Provide your comments or questions through the online comment form below.

Email your comments or questions directly to the project contact: Andrew La Croix, Project Engineer, Oxford County, alacroix@oxfordcounty.ca | 519-539-9800, ext. 3121

Online. Follow Oxford County on social media for construction updates or visit www.oxfordcounty.ca/construction

March 10, 2026


Oxford Road 35 (Devonshire Ave) reconstruction in Woodstock

Spring - November 2026


Oxford County is continuing a multi-year reconstruction project to improve Oxford Road 35 (Devonshire Avenue) in Woodstock.

Phase 2 of this project, beginning in spring 2026, includes construction located just east of Wellington Street to just east of Knightsbridge Road. Work includes:

  • sanitary sewer, storm sewer and watermain replacement and repairs;
  • road replacement with a three-lane cross section;
  • bike lanes and sidewalks; and,
  • traffic signal installation for a pedestrian crossing at Victoria Street.

Planned future phases include different sections of Devonshire Avenue in subsequent years, extending east to Oxford Road 4 except for the area between Lansdowne Avenue and Woodall Way.

Please note that construction schedules are weather dependent and subject to change based on site conditions, contractor availability and other operational demands.


Detour routes


Learn more

Public Information Centre (PCC). A public information meeting was held on February 24, 2026, to allow the public to view plans and discuss the project with Public Works Engineering staff.

Comment form. Provide your comments or questions through the online comment form below.

Email your comments or questions directly to the project contact: Andrew La Croix, Project Engineer, Oxford County, alacroix@oxfordcounty.ca | 519-539-9800, ext. 3121

Online. Follow Oxford County on social media for construction updates or visit www.oxfordcounty.ca/construction

  • Public information meeting for Oxford Road 35 (Devonshire Ave) reconstruction

    Share Public information meeting for Oxford Road 35 (Devonshire Ave) reconstruction on Facebook Share Public information meeting for Oxford Road 35 (Devonshire Ave) reconstruction on Twitter Share Public information meeting for Oxford Road 35 (Devonshire Ave) reconstruction on Linkedin Email Public information meeting for Oxford Road 35 (Devonshire Ave) reconstruction link

    February 12, 2026


    Spring - November 2026

    Oxford County is continuing a multi-year reconstruction project to improve Oxford Road 35 (Devonshire Avenue) in Woodstock.

    A public meeting has been scheduled to allow the public to learn more about Phase 2 of the project (2026), view plans, and ask questions.

    Tuesday, February 24, 2026
    Drop in: 5:00 – 7:00 p.m.
    Oxford County Administration Building
    21 Reeve Street, Woodstock


    Construction

    Phase 2 of this project, beginning in spring 2026, includes construction located just east of Wellington Street to just east of Knightsbridge Road. Work includes:

    • sanitary sewer, storm sewer and watermain replacement and repairs;
    • road replacement with a three-lane cross section;
    • bike lanes and sidewalks; and,
    • traffic signal installation for a pedestrian crossing at Victoria Street.

    Planned future phases include different sections of Devonshire Avenue in subsequent years, extending east to Oxford Road 4 except for the area between Lansdowne Avenue and Woodall Way.

    Please note that construction schedules are weather dependent and subject to change based on site conditions, contractor availability and other operational demands.


    Learn more

    You can learn more about this project or submit feedback in the following ways.

    Attend the Public Information Centre (PCC). A PIC has been scheduled to allow the public to view plans and discuss the project with Public Works Engineering staff:
    Tuesday, February 24, 2026 | Drop in: 5:00 – 7:00 p.m.
    Oxford County Administration Building, Main Lobby 21 Reeve Street, Woodstock

    Comment form. Provide your comments or questions through the online comment form below.

    Email your comments or questions directly to the project contact: Andrew La Croix, Project Engineer, Oxford County, alacroix@oxfordcounty.ca | 519-539-9800, ext. 3121

    Online. Follow Oxford County on social media for construction updates or visit www.oxfordcounty.ca/construction

    2026 Detour routes


Page last updated: 10 Mar 2026, 12:05 AM