Stage 1 ­deck concrete pour in April

April 5, 2024


Construction work on the Oxford Road 59 (Vansittart Avenue) bridge in Woodstock is ongoing from February until December 2024


Construction is progressing on schedule. Over the past six weeks, the contractor has completed a number of steps to prepare for bridge jacking and the Stage 1 ­deck concrete pour, including installing access platforms and pedestrian hoarding beneath the bridge to protect the trail and its users.

Concrete removals are also ongoing as the contractor works to remove the existing sidewalk, curb, asphalt, and decking on the west side of the bridge.

When the bridge jacking takes place later in April, motorists can expect two approximately 15-minute closures for one day. Please watch for updates at www.oxfordcounty.ca and on our social media channels for the date these closures will take place.

Share Stage 1 ­deck concrete pour in April on Facebook Share Stage 1 ­deck concrete pour in April on Twitter Share Stage 1 ­deck concrete pour in April on Linkedin Email Stage 1 ­deck concrete pour in April link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>